An existing filter arrangement had to be modified for a drinking water production company. Based on a study the client had carried out itself, the Engineering department mapped the existing surroundings with a 3D scan. Then, in consultation with the client, we looked for the best pipe route.
Because the 3D scan served as the basis in the 3D drawing software, the route could be determined in a short time. Based on the design the client approved, the Pipework department produced the pipework in 316L stainless steel.
Our service department carried out the on-site installation to a tight schedule. From engineering and fabrication through to installation, the project took 10 weeks in total.