Engineering
Project process: from 3D scan to installation
How a project runs at Technische Alliantie differs from one assignment to the next. The projects on this site often follow the same sequence: measuring, designing in consultation with the client, building in the workshop and installing on site. Technische Alliantie coordinates the whole, from engineering and project management through to commissioning, and is your point of contact in every phase. Below we follow one real project: the modification of a filter arrangement at a drinking water plant.
The project: a filter arrangement at a drinking water plant
A drinking water company wanted an existing filter arrangement modified. The client had already carried out its own research into what needed to change. Technische Alliantie’s work started on that basis.
Step by step
Measuring with a 3D scan
The Engineering department mapped the existing surroundings with a 3D scan.
Determining the pipe route, together with the client
The pipe route was explored in consultation with the client. Because the scan served as the basis, the route could be determined in a short time.
Approval of the design
The pipework was made on the basis of the design the client had approved. Only then did the work go to the workshop.
Fabrication in the workshop
The Pipework department made the pipework in 316L stainless steel in our own workshop. You can read more about that work under piping systems and pump technology.
Installation on site
The service department installed the pipework on site, to a precise schedule. From engineering and fabrication through to installation, the project took 10 weeks. View the project
Who does what in a project
The engineers do the thinking and the project management. The build preferably goes to our own workshop and the other disciplines within the alliance, and where necessary to the established partners for civil engineering, electrical engineering and structural steelwork.
The same division can be seen with the condensate tank in Weert: the engineering department made a 3D scan and a 3D model, the tank was prefabricated in the workshop, and setting it in place, including the modifications, took 22 hours non-stop.
The whole process or a single phase
You do not have to entrust the whole process to us. You can join or leave at any phase: have only the design made, or the entire process from initiative to realisation and maintenance. The six phases are explained under project management and work preparation.